Scope of work: provide all labor, equipment, materials, and transport needed in performing all work required under this project consists of providing all labor, equipment, and materials to replace (2) chillers, (1) dual cell cooling tower, associated (7) pumps and appurtenances for the chillers and cooling tower, and all outside air duct work. New duct work will be stainless steel. Reconfigure piping to chillers. Seal all ducts at end of construction prior to operation of HVAC system. Demo 6 pillars to the cooling tower and match pad according to cooling tower specs. Upgrade building HVAC controls. Provide temporary cooling and project phasing in coordination with building user and activities.
Site visit 07/30/26 at 10:30am- meet in the parking lot of B352. Badge applications due to ABBA by noon 07/24/26.
RFI's due to ABBA by 10 am 07/31/26.